AMO FOR THE CONSTRUCTION OF A METHANIZATION UNIT – TRIFYL
OUR MISSION :
Project management assistance for the construction of a 120,000 t/year residual household waste treatment unit for material and energy recovery.
This ambitious project, in synergy with the 2 other units at Blaye-Les-Mines and Labruguière, will make it possible to recover over 80 % of household waste, reduce greenhouse gases by 23 % and multiply green energy production by 3.
CAPACITY :
- 12 000 t de biodéchets,
- 85 000 t of household waste
- 20 000 t of bulky waste.
CALENDAR :
Completion of work on the Labessière-Candeil site is scheduled for autumn 2023 and commissioning for early 2024