Construction of a biomass heating plant and associated heating network – Amnéville
PROJECT STAGES :
- Project feasibility studies
- Comparative studies of possible assembly, realization and operation models
- Project definition APD level
- Consultation of companies for design, construction and operation
- Commercialization of subscription policies
- Monitoring of work completion
- Assistance with acceptance operations
- Assistance during the first years of operation
MISSION :
ATMO – Assistance Technique à Maîtrise d’ouvrage
TECHNICAL DATA :
- 2 Biomass boilers 2 and 1 MW and 2 Gas boilers 4.5 MW
- 10 km of network and 25 delivery points
DELIVERY :
January 2019
INVESTMENT :
8,100 K€HT