Construction of a wood-fired heating plant and extension of the heating network in Gennevilliers
PROJECT TEXT :
Development of the existing urban heating network in the Luth and Madeleine districts, historically supplied by a gas boiler plant and a gas cogeneration plant.
Construction of a wood-fired boiler with the aim of achieving a wood coverage rate of 50 %.
OUR MISSION :
Complete project management (process, civil engineering and VRD-Infra), excluding preparation and submission of the building permit. preparation and submission of PC.
Design of hydraulic diagram interconnecting the two boiler plants in order to optimize the operation of the cogeneration and to maximize the wood coverage rate.
WORK DESCRIPTION :
Extension of the heating network, with the creation of 1.6km of DN300 trench
Construction of a wood-fired a 17MW wood-fired boiler plant with 2 generators equipped with generators equipped with bag filters and a 2500 m3 silo with a tubed screw for extraction for extraction
Construction on a 5700 m2 plot composed of partially polluted soil and requiring the installation of foundations
costs and planning
Amount of work : 14 M€ HT
- Wood boiler room structural work/R&D : 6,4 M€ HT
- Wood boiler room technical lots : 5,8 M€ HT
- Heat network network : €1.7 M ex VAT
Project schedule :
- PC filing : July 2014
- Studies : February 2014
- Construction start : December 2015
- First firing : october 2016
- Commissioning of wood boilers : December 2016