CONSTRUCTION OF WASTEWATER TREATMENT PLANT – SIEPAM
OUR MISSION :
Project management assistance, design and construction.
PROGRAM :
Programming. Technical validation, MOE and works.
EXISTINGPROBLEMS :
- Creation of a 28,000 EQH WWTP
- Seasonal load variation (1 to 8)
- Network collected from 900 to 1,500 m altitude
- Water treatment by membrane process
- Sludge treatment by centrifugation
- Collection network with overhead crossings (220 m span, ON 250)