Our mission :

Complete project management : EP, AF, AVP, PRO, ACT, EXE, DET, AOR AMO for the drafting of all environmental and administrative files.

AMO for additional assignments : geophysics, geotechnics, pumping tests, topography, …

Program :

Creation of a new AEP catchment in the Drac aquifer and all the networks and pumping station needed to supply the 6 reservoirs at Vif and Les Saillants du Gua.

Specific constraints :

  • Very short deadlines : Design 1 year, Realization 1 year,
  • Environmental constraints : catchment within the Isles du Drac Regional Nature Reserve,
  • Traffic management : major work on the main avenue of the commune of VIF,
  • Operating synoptic of the adduction network totally reversed,
  • Presence of asbestos networks.
  • Grenoble
  • GRENOBLE-ALPES METROPOLE
  • 2018